Control Fronius GEN24 inverter and battery via Modbus TCP from Homey Pro.
Requirements
- Homey Pro (local apps)
- Fronius GEN24 with Modbus TCP enabled
- Optional: Fronius Smart Meter (needed for import/export based cards)
Inverter setup (web UI)
1) Communication -> Modbus
- Mode: TCP Server
- SunSpec Model Type: int + SF
- Port: 502
- Allow Control: ON
- Note Meter Address Offset (Smart Meter Unit ID, usually 200)
2) Grid Regulations / Export Limitation (optional)
- Set Maximum grid feed-in power in the inverter UI
- This is used by "Use inverter export limit"
3) Battery charging from grid (optional)
- Enable if you want grid charging
Add device in Homey
- Enter inverter IP/hostname, port and Unit ID (default 1)
- If you use a Smart Meter, set Smart Meter Unit ID (default 200)
Important settings in the app
- Installed PV/site capacity (Wp): total installed PV capacity in Wp (sum of all arrays)
Used by "Limit inverter production to X W"
- Battery max charge/discharge (kW) and optional battery capacity (kWh)
Used to convert W to percent for storage control
- Inverter max AC power (kW) fallback
Notes
- Import-capped charging and zero export run in a loop until stopped.
- Intervals are in seconds (min 30 s for import-capped charging).
- Modbus control can affect inverter and battery behavior. Use at your own risk.
Les mer ›
Flow-kort
Klikk på en enhet ovenfor for å kun vise relaterte Flow-kort.
Når …
Fronius GEN24
Strømmen ble endret
Fronius GEN24
Export exceeds Threshold (W) W
Fronius GEN24
Import exceeds Threshold (W) W
Fronius GEN24
Limited charging started
Fronius GEN24
Limited charging stopped
Fronius GEN24
Peak shaving started
Fronius GEN24
Peak shaving stopped
Fronius GEN24
Auto zero export started
Fronius GEN24
Auto zero export stopped
Og …
Fronius GEN24
Limited charging is active
Fronius GEN24
Peak shaving is active
Fronius GEN24
Auto zero export is active
Så …
Fronius GEN24
Disable inverter export limit
Fronius GEN24
Use inverter export limit
Fronius GEN24
Force discharge now with Discharge power (W) W
Fronius GEN24
Reset battery control
Fronius GEN24
Set min charging to Charge power (W) W
Fronius GEN24
Discharge now with Discharge power (W) W
Fronius GEN24
Set export limit to Max production (W) W
Fronius GEN24
Set max charging to Max charge (W) W
Fronius GEN24
Start limited charging up to Max charge (W) W (max import Max grid import (W) W, fuse Main fuse per phase (A, optional) A/phase, interval Check interval (s, min 30) s)
Fronius GEN24
Keep import under Peak target (W) W (duration Duration (minutes, 0 = until stopped) min, interval Update interval (seconds) s)
Fronius GEN24
Set production limit to Max production (W) W
Fronius GEN24
Start auto zero export (interval Update interval (seconds) s, duration Duration (minutes, 0 = until stopped) min)
Fronius GEN24
Stop limited charging
Fronius GEN24
Stop peak shaving
Fronius GEN24
Remove production limit (restore 100%)
Fronius GEN24
Stop auto zero export